The PTC Explains Suspended Project

2009 March 31 at 11:47 am (Pennsylvania Turnpike Commission, Politics, Tredyffrin Twp.) (, , )

PTC’s Open Letter

PTC has suspended “further engineering development” of Mileposts 320 thru 326 “in reaction to major cost increase required to meet the demands for alternative stormwater-control methods that include features such as spray irrigation and underground storage.”  They believe the storm water controls will add 50% to construction costs.  ”Beyond the projected construction-cost increase of $75 to $100 million, the proposed stormwater-control methods also would involve ongoing, lifelong maintenance and operation costs that far exceed commonly employed treatment systems.”  Read more… 

Also suspended is the bidding and construction on the Rte 29 Interchange Project.  

Isn’t this good news for Tredyffrin residents?  

Not for the owners of any of the 106 homes slated for full or partial condemnation.   Even though their properties are shown on the PTC plans, these folks were not served legal papers condemning their properties.  Can they sell their homes?  Almost certainly not.  They are now totally in limbo.  

- A Pen

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

Gravatar
WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.